Before choosing branch equipment around an opening date, list the products to be sold, expected delivery flow, and when permanent space will be ready. Mark unknown dates as assumptions.
Add lease start, power and cold-space commissioning, first goods receipt, staff training, and opening day to one schedule. State when each item of equipment is needed and who decides if dates slip.
Get dated quotes for a temporary portable option and permanent installation. Compare setup, connections, transport, maintenance, usable capacity, and later reuse or return terms on separate lines.
Verify required storage conditions against product labels and site procedures. If the temporary option's measured and documented use does not meet them, revise the opening plan with the quality and operations leads.