Entry into force is the day the text legally exists, application is the day its rules start operating, and a target date is the day a given rate starts being required. Mixing them up leads either to needless haste or to being late.
| Date | What happens | Type |
|---|---|---|
| 11 February 2025 | Regulation entered into force | Entry into force |
| 12 August 2026 | Most rules start to apply | Application |
| 1 January 2030 | At least 40% of transport packaging must be reusable containers in a re-use system | Target |
| 1 January 2040 | Operators are to endeavour to raise that rate to 70% | Target |
The regulation does not bind a business in Türkiye directly. In an export chain the demand comes from the buyer, so label each condition as a legal provision or a buyer condition. At home, the deposit scheme for beverage packaging has run nationwide since 1 July 2026, independent of the EU calendar.